Project Update: Mead Market Street Complex

By March 23, 2020 No Comments
Project Overview:

Market Street Complex consists of four different projects for Mead School District. The Maintenance Facility was constructed for Mead’s maintenance staff. This building houses shops for their electricians, plumbers, painters, carpenters etc. The Transportation Facility is used for servicing the district’s buses from tire changing to complete engine replacements. Construction of this facility included canopies to house the approximate 100 buses the district has. Across Market Street, we are currently building the Performing Arts and Athletic Complex. This portion of the project includes a new 4,500 seat stadium (name TBD) with synthetic turf, two support buildings for concessions and locker rooms, three natural grass soccer/lacrosse fields, and an addition to the gyms that serviced Mead Junior High while it was around (now demolished under our project) Lastly, at the corner of Freya and Hastings we are constructing a brand new 65,000 sf elementary school, Creekside Elementary.

Current Status:

Take a look at the photo carousel below and check out the exciting updates for this project.

  • M&T- Completed mid-December of 2019. These buildings are now occupied and in full swing.
  • Creekside Elementary – CMU Veneer complete, window installation ongoing at exterior. Sheetrock installation nearly complete at area 300 which is the last wing we have to rock. Areas 100 and 300 are painted out with vinyl wall covering installed. PLAM panels are installed at area 200 first and second floor. Bathroom tile ongoing in area 200. Anticipated project completion July 2020.
  • PA&A – Dressing and Gameday Service Buildings are dried in with exterior and interior CMU complete. MEP rough in on going in each. Fields are graded out. Currently hauling excess material (approx. 15,000cy of soil) off site. Framing and sheeting ongoing at the gym addition. The existing Mead Junior High, originally Mead High School, has been demolished. Remains need to be hauled off and footings/foundations removed and demo will be complete. Anticipated project completion August 2020.