Project Update: Farwest Steel

By August 3, 2023 August 30th, 2023 No Comments

Farwest Steel – Steel Distribution Facility
Location: Post Falls, ID
Anticipated
Completion: December 2023

Project Summary:

This project is a concrete tilt-up building with 100,000 SF of warehouse and material processing space and 8,000 SF of office space for a steel distribution company based out of Eugene, Oregon. There are 64 total concrete panels on this project: 56 warehouse panels and 8 office panels. On the interior of the warehouse, there are three large bays which run the length of the building. Each bay will have one 10-ton bridge crane, with plans to add two more 10-ton cranes and a 30-ton crane with a rotator in the future. There are four total truck bays which run the width of the building. At the northernmost truck bay, there is a rail spur which enters the building on the west side and ends at the opposite side of the building. The total property size is about 440,000 SF (10.1 acres) with enough space for a second, smaller building. This secondary building is currently part of phase II and is not part of the immediate construction plans.

Recently completed milestones:

Lifting and bracing of all 64 concrete tilt-up panels was completed on 6/26. Additionally, our ironworkers recently placed the final steel joist on 7/19.

Current Work in Progress:

  • Electrical rough-in is ongoing in the warehouse
  • Metal decking is being installed with roof curbs following after
  • Excavation, backfill, and installation of offsite utilities and onsite utilities
  • Joist X bracing between joists and concrete panel wall

Upcoming work:

  • Installation of bridge crane runway beams and crane rails
  • Exterior light poles
  • Office joists and decking
  • Office slab on grade placement
  • Warehouse pourback strip placement
  • Install roofing
  • Curbing along Seltice Way to be placed