Hydrant Fueling System Addition
Fairchild Air Force Base, WA

Budget: $11,000,000

New Type III Pressurized Hydrant Fueling System at Fairchild Air Force Base with an addition to the existing system featured two 10,000 BBL JP-8 storage tanks, pumphouse, fueling pumps, along with demolition and replacement of PCC Airfield Pavement. Project completed in April 2002 two month ahead of schedule. Awarded Corps of Engineers 2001 Military Contractor of the Year.