Kaiser Aluminum Fabricated Products
Spokane, WA
Budget: $60,000,000
Garco Construction has completed numerous projects for Kaiser Aluminum, including the 70,000 SF Carbon Baking Furnace building that involved the excavation of a 20' deep basement and the forming and pouring of the 3' foundation mat and 2' thick walls. Garco Construction furnished and installed two 35 ton overhead cranes, runway beams and supporting office structures. We are appreciative of our longstanding relationship (since 1990) and continued work with Kaiser.
| |
|